Siting and Construction of Any New Mobile Service Support Structure and Facilities and Class 1 Collocation:

(a) Application Process. A zoning permit is required for the siting and construction of any new mobile service support structure and facilities for a Class 1 Collocation if the following substantial modifications are added to the existing mobile service support structure:

1. An increase in the overall height of the structure by more than twenty (20) feet, for structures with an overall height of two hundred (200) feet or less.

2. An increase in the overall height of the structure by 10% or more, for structures with an overall height of more than two hundred (200) feet.

3. An increase in width of the support structure by twenty (20) feet or more, measured at the level of the appurtenance added to the structure as a result of the modification.

4. An increase in the square footage of an existing equipment compound to a total area of more than 2,500 square feet.

(b) A zoning permit application must be completed by any applicant and submitted to the Division of Planning Operations (hereinafter referred to as the “Department”). The application must contain the following information:

1. The name, business address and phone number of the contact individual for the applicant. The applicant should include an email address if available.

2. The location of the proposed affected support structure.

3. The location of the proposed mobile service facility.

4. If the applicant does not own the site or the tower, the applicant must provide an agent letter or lease agreement that provides consent from the property owner. The applicant should also provide the legal descriptions and amount of property leased.

5. If the application is to substantially modify an existing support structure, a construction plan which describes the proposed modifications to the support structure and the equipment and network components, including antennas, transmitters, receivers, base stations, power supplies, cabling, and related equipment associated with the proposed modifications. The construction plan shall include a sketch concept or rendering of the site and a scaled site plan which shows property lines, lease areas, setback distances, structures including support structure, buildings, equipment pads, and fencing.

6. If the application is to construct a new mobile service support structure, a construction plan which describes the proposed mobile service support structure and the equipment and network components including antennas, transmitters, receivers, base stations, power supplies, cabling, and related equipment to be placed on or around the new mobile service support structure. The construction plan shall include a sketch concept or rendering of the site and a scaled site plan which shows property lines, lease areas, setback distances, structures including support structure, buildings, equipment pads, and fencing. The Department may also request the submittal of propagation maps.

7. If an application is to construct a new mobile service support structure, an explanation as to why the applicant chose the proposed location and why the applicant did not choose collocation, including a sworn statement from an individual who has responsibility over the placement of the mobile service support structure attesting that collocation within the applicant’s search ring would not result in the same mobile service functionality, coverage and capacity; is technically infeasible; or is economically burdensome to the mobile service provider.

(c) An application for a zoning permit shall be made available by the Department upon request by any applicant.

(d) Completed Applications. If an applicant submits to the Department an application for a zoning permit to engage in an activity described in this ordinance, which contains all of the information required under this ordinance, the Department shall consider the application complete. If the Department does not believe that the application is complete, the Department shall notify the applicant in writing, within ten (10) days of receiving the application, that the application is not complete. The written notification shall specify in detail the required information that was incomplete. An applicant may resubmit an application as often as necessary until it is complete.

(e) In the event the department determines that it is necessary to consult with a third party in considering a zoning permit application, all reasonable costs and expenses, excluding travel expenses, associated with such consultation shall be borne by the applicant. Failure to pay such costs and expenses or to provide information requested by the department shall be grounds for denial or revocation of the zoning permit.

(f) Department Responsibilities. Within ninety (90) days of its receipt of a complete application, the Department shall complete all of the following or the applicant may consider the application approved, except that the applicant and the Department may agree in writing to an extension of the ninety (90) day period:

1. Review the application to determine whether it complies with all applicable aspects of the County’s zoning ordinance.

2. Make a final decision whether to approve or disprove the application.

3. Notify the applicant, in writing, of its final decision.

4. If the decision is to disprove the application, include with the written notification substantial evidence which supports the decision.

(g) Disapproval. The Department may disapprove an application if an applicant refuses to evaluate the feasibility of collocation within the applicant’s search ring and provide the sworn statement described under paragraph 12.24.040 (b)6.

(h) Application of Set Back/Fall Zone. If an applicant provides the Department with an engineering certification showing that a mobile service support structure, or an existing structure, is designed to collapse within a smaller area than the set back or fall zone areas required in a zoning ordinance (§ 12.38.010(b)) that zoning ordinance does not apply to such a structure unless the Department provides the applicant with substantial evidence that the engineering certification is flawed.

(i) Fees. The fee for a zoning permit relating to construction of a new mobile service support structure and facility or for a Class 1 Collocation is listed in the Department’s Fee Schedule.

(j) Limitations. The zoning permits for Siting and Construction of any new mobile service support structure and facilities and for any Class 1 Collocation shall only be granted provided the following conditions exist:

1. The applicant has obtained Federal Communications Commission (FCC) license numbers and registration numbers if applicable.

2. The applicant and/or agent have copies of Findings of No Significant Impacts (FONI) statement from the Federal Communications Commission (FCC) or Environmental Assessment or Environmental Impact Study (EIS), if applicable.

3. The applicant and /or agent have copies of the determination of no hazard from the Federal Aviation Administration (FAA) including any aeronautical study determination or other findings, if applicable.

4. The applicant and/or agent have copies of an Affidavit of Notification indicating that all operators and owners of public or private airports and landing strips located within five (5) miles of the proposed site have been notified via certified mail.

5. If the location of the proposed mobile service support structure or mobile service facility is on leased land, the lease agreement does not preclude the lessee from entering into leases on the site with other provider(s) and there is no other lease provision operating as a bar to collocation of other providers. [Code § 12.18.1-4.]