Stormwater permits shall be subject to all of the requirements of this section. Violation of any permit requirement shall cause the permit holder and any other responsible party to be subject to enforcement action under Section V. Upon issuance of a stormwater permit, the permit holder and any other responsible party shall be deemed to have accepted these requirements. General requirements include all of the following:

(a) Other Permits. Compliance with the final stormwater plan does not relieve the applicant or other responsible party of the responsibility to comply with other applicable federal, state, and local laws and regulations. P&D may require the applicant to obtain other permits or plan approvals prior to issuing the stormwater permit.

(b) Approved Plans. All best management practices shall be installed and maintained in accordance with approved plans and construction schedules. A copy of the approved plans shall be kept at the construction site at all times during normal business hours.

(c) Plan Modifications. P&D shall be notified of any modifications (including field changes) proposed to be made to the approved plans. P&D may require proposed changes to be submitted for review prior to incorporation into the approved plans or implementation. Any modifications made during plan implementation without prior approval by the Project Engineer under Section 17.08-1(g) and P&D are subject to enforcement action.

(d) Meetings. A minimum of one meeting shall be held prior to beginning construction to discuss the contractor roles and schedule of the project. This meeting shall be referred to as the preconstruction meeting. At a minimum, the Project Engineer, the Contactor, the Owner/Developer, and appropriate Town Representatives shall attend the meeting. P&D shall reserve the right to require additional attendees as necessary. The meeting shall be scheduled with P&D, with no less than a five (5) working day notice. Financial assurance in accordance with Section 17.08-3 shall be in place prior to holding this meeting.

(e) Notification

P&D shall be notified at least 3 working days before beginning any construction work in conjunction with approved plans. P&D shall also be notified of proposed plan modifications under Section 17.08-1(c), and within 1 working day of completing construction of a stormwater BMP. P&D may require additional notification according to a schedule established by P&D as determined at the preconstruction meeting so that practice installations can be inspected during construction. A minimum of 1 working day notice must be given in these circumstances.

(f) P&D Access. P&D or its designee shall be permitted access to the site for the purpose of inspecting the property for compliance with the approved plans and other permit requirements.

(g) Project Engineer/Landscape Architect

(h) The permit holder shall provide an engineer licensed in the state of Wisconsin to be responsible for achieving compliance with approved construction plans, including the implementation of the approved inspection plan and verification of construction in accordance with Section 17.08-4. If warm season or wetland plantings are involved, the permit holder shall also provide a registered landscape architect or other qualified professional to oversee and verify the planting process and its successful establishment.BMP Maintenance

The permit holder, in accordance with approved plans and applicable technical standards, shall maintain permanent stormwater management practices until maintenance responsibility is transferred to another party or unit of government pursuant to the recorded maintenance agreement.

(i) Emergency Work. The permit holder authorizes P&D, in accordance with the enforcement procedures of Section V, to perform any work or operations necessary to bring stormwater management practices into conformance with the approved plans and authorizes P&D to charge all applicable costs against the financial assurance as in Section 17.08-3.

(j) Other Requirements. P&D may include other permit requirements that P&D determines are necessary to ensure compliance with this ordinance. [Code § 17.08-1.]